38-Booth Multi-Floor Office Pod Project in Shenzhen

This office pod project is located in Shenzhen, China. The client is a well-known cosmetics R&D and promotion company, and the project covers four floors of office space.

The project included 38 booths — 24 × 1P office pods, 10 × 4P meeting pods, and 4 × 6P meeting booths — to support private calls, internal communication, video discussions, visitor reception, and small meetings.

The project has been completed and delivered. This case mainly highlights the early planning and delivery preparation process.

Request Support for a Similar Multi-Floor Project

4 Floors / 38 Booths

LOCATION

Shenzhen, China

SCOPE

4 floors / 38 booths

PRODUCT MIX

24 × 1P / 10 × 4P / 4 × 6P

STATUS

Completed handover confirmed

Pod mix / packing adjustment / installation support

3d planning visual for a bangkok office booth planning support case

Completed handover view after site assembly.

A simplified reference for multi-floor booth placement

A simplified reference for multi-floor booth placement

Coordinating Office Pods Across a Four-Floor Layout

The project was planned around the client’s need for private and semi-private spaces across several work areas, giving employees dedicated places for communication and discussion.

Across four floors, the office plan had to support private calls, internal communication, video discussions, visitor reception, small group talks, and short meeting needs within the new workplace layout.

Before sending the inquiry, the customer already had a complete floor plan showing booth locations, furniture placement, and key dimensions. The office pod planning therefore needed to fit the existing layout instead of being treated as a separate product purchase.

Coordination Focus

Multi-floor planning

Booth requirements were reviewed across four office floors.

Existing office planning

Booth planning needed to fit the customer’s workplace layout.

Capacity direction

1P, 4P, and 6P booths were planned for different communication and meeting needs

Project requirements

Before project planning, the customer should confirm exterior and interior color options, network access needs, ventilation configuration, and any supplier documentation required for the project.

During the project, exterior and interior color options, network access, and ventilation requirements should be confirmed together with the packing method and the on-site handling plan after delivery.

Product Mix and Use Plan for a 38-Booth Office Project

The project did not use one booth size for every office area. Instead, the office pod plan combined 1P, 4P, and 6P booths so different communication needs could be matched with different capacity levels across the four-floor office layout.

The final project mix included 38 booths: 24 × 1P office pods, 10 × 4P meeting pods, and 4 × 6P meeting booths. Each capacity had a clear role in the project.

1P Office Pod

Individual communication points

4P Meeting Pod

Small discussions

6P Meeting Booth

Larger discussion spaces

38-Booth Project Mix

1P Pods

24

4P Pods

10

6P Booths

4

Total 38 booths

24 UNITS

1P Office Pods

Model C

Planned for private calls, video discussions, and individual communication points across the office floors.

10 UNITS

4P Meeting Pods

Model B

Planned for small group discussions, internal communication, and short meeting needs.

4 UNITS

6P Meeting Booths

Model A

Planned for larger discussion spaces, visitor reception, and small meetings within the project layout.

This mix gave each booth capacity a clear planning role. The 1P booths were planned for individual communication points, while the 4P and 6P booths were assigned to small meeting and discussion needs across the office layout. In this case, Model A, Model B, and Model C refer to the booth series selected for each capacity.

IMG_ALT

Booth Placement Planning Across Four Office Floors

The project started with workstation layout planning, followed by planning how different booth sizes would be distributed across the four-floor office space.

Booth placement was planned in relation to nearby workstation areas, with wall-side positions preferred where possible. Where conditions allowed, the doors were oriented toward the corridor for easier access.

Instead of applying one placement rule to every floor, the layout plan matched each booth capacity with the surrounding work tasks.

Layout Planning Points

???

Instead of applying one placement rule to every floor, the layout plan matched each booth capacity with the surrounding work tasks.

Wall-side placement

Booth positions were planned along suitable wall-side areas where the layout allowed.

Corridor-facing access

Where possible, the doors were oriented toward the corridor for easier access.

Workstation distance

Booth placement took the distance from desk areas into account to help reduce crowding.

Capacity matching

1P, 4P, and 6P booths were planned according to different communication and meeting needs.

Project Requirements Reviewed Before Production Preparation

In addition to booth quantity and layout, several technical configurations and document-related items need to be confirmed before production begins.

The review covered project-specific documentation needs, configuration requirements, ventilation and network requirements, and the exterior finish for this office space If acoustic, VOC, or SGS / ISO-related evidence is required, please follow the company’s document review process to obtain the relevant files.

Requirement Review Areas

Acoustic evidence

Acoustic documentation was part of the project requirement review.

VOC evidence

VOC-related evidence was reviewed as part of the project documentation requirement.

Smart function requirements

Occupancy sensor and automatic air refresh requirements were reviewed during project confirmation.

Ventilation requirements

Low-noise ventilation was included in the project requirement review.

Network access

Internal network connection requirements were checked as part of the office planning input.

Exterior and interior finish

A deep blue exterior finish was selected to match the office’s visual style.

IMG_ALT

Finish Direction

A deep blue exterior finish was selected for this project to match the office’s overall visual direction.

Each project may have different requirements. The details and requirements of this project do not mean that every project, model, or configuration will achieve the same acoustic performance.

Site Conditions and Packing Adjustment

Before production and packing, the project’s specific site access and on-site handling conditions should be confirmed with our project team.

The unloading point was about 100 meters from the elevator. The ground condition was uneven, and forklift access was not suitable for the moving path. Because the booths had to be moved across the site before assembly, the packing method needed to support easier sorting, handling, and movement after arrival.

IMG_ALTIMG_ALT

This packing method was adjusted based on the specific needs of this project. It does not mean that the same packing method will be used for every project order.

Project-Specific Packing Adjustment

For this project, the original full-box packing method was adjusted to a loose packing arrangement.

Large booth components were packed separately by part type, including panels, ceiling parts, and base sections. Sequence numbers and product size information were marked on the packages to help the site team identify, sort, and organize the products by floor after arrival.

Packing method adjustment

Full-box packing direction was adjusted into loose packing for easier site-side sorting, handling, and movement after arrival.

Long moving distance from unloading point to elevator

Packing needed to support site-side sorting and movement

Uneven ground condition

Components were prepared for more controlled handling after arrival.

Forklift access not suitable for the moving path

Loose packing was planned to reduce reliance on forklift movement inside the site.

Multiple booth types and quantities

Package information helped organize different booth components.

Large components packed separately

Panels, ceiling parts, and base sections were packed by part type for site-side handling.

Pre-shipment Assembly Reference Before Packing

Before final packing, different booth sizes and model types were trial-assembled to confirm that all components were complete before delivery.

Photos and video references were prepared and shared as pre-shipment project references before packing. These materials helped the project team refer to the booth structure, model types, and assembly sequence before the components were organized for delivery.

Trial Assembly Reference

This helped our QC team review the booth structure, model types, and component completeness before shipment.

IMG_ALT

Arrival Review Materials for Site Assembly

Alongside packing preparation, we also prepared a complete packing list to help the customer check the goods after arrival and support later on-site assembly.

These materials were prepared to support project handover. They should not be described as a full QC report, final site acceptance proof, or a guarantee of post-installation performance.

01

Guidance

02

Cheklists

03

Identification

04

Feedback path

Installation manual

Provided assembly guidance for the site-side team.

Trial assembly photos / video references

Used as pre-shipment project references before packing.

Arrival checklists

Helped the site team review delivered booth components after arrival.

Package identification information

Helped identify separated booth components after arrival.

Photo record guidance

Helped the site team record package, glass, door, frame, accessory, label, or box information when arrival review was needed.

Feedback process

Provided a clear way to report arrival-side issues for follow-up.

Installation Support and Project Handover

For this project, professional installers were arranged to complete the on-site installation based on the customer’s needs.

The project included 38 booths across four office floors, so the assembly work needed to follow the planned layout, site moving conditions, package sequence, and prepared handover materials. After the booth components arrived on site, the installation team supported the on-site assembly according to the project plan.

Site Assembly Coordination

In this multi-floor office pod project, installation support was provided, and the packing method was adjusted based on actual site conditions.

  • Planned layout and package sequence
  • Factory-arranged assembly support
IMG_ALT

Factory-arranged on-site assembly support was provided for this project.

Handover Status

Handover Confirmed

Handover was confirmed after site assembly.

Site Assembly and Completed Handover

For this project, a factory-arranged installation team supported the on-site assembly stage. Four installers completed the on-site assembly work for 38 booths over three days.

This case shows how installation support, package sequence, and handover preparation were coordinated for one multi-floor office pod project.

38

booths across four floors

4

installers

3

days for this project

Installation Support Summary

ItemCase Detail
Project scope38 booths across four office floors
Installation supportFactory-arranged site-side assembly support for this project
Site-side assemblyCoordinated with the project layout, package sequence, and handover materials
Handover statusCompleted handover confirmed after site assembly

Spare Parts Prepared for Project Handover

Spare parts were prepared as part of the handover package for this multi-floor office pod project.

These spare parts helped support project handover and follow-up coordination if replacement parts were needed.

Handover Support Context

We organized the spare parts list, and related information, then sent them to the customer to support later on-site installation.

Project Review Note

For similar project orders, the spare parts list and packing list are confirmed with the customer based on the final order quantity and selected product models.

Spare Parts Prepared

4 sets

Door handler

2 sets

Locks

4 sets

LED lights

5 units

Fans

5 units

Socket ports

Project Image Gallery

This gallery brings together selected visuals from the multi-floor office pod project, including layout planning, product mix, packing preparation, pre-shipment assembly references, on-site assembly support, handover views, and spare parts prepared for project handover.

The images show different project stages, from planning and preparation to on-site assembly and handover.

IMG_ALT

Completed handover view

Handover view after site assembly.

IMG_ALT

Trial assembly reference

Pre-shipment assembly reference before packing.

Project Image Note

The gallery images show project stages and preparation details. They should not be understood as customer usage results, employee feedback, customer satisfaction, final acceptance, or post-installation performance claims.

Gallery Summary

From layout planning and packing preparation to pre-shipment assembly references and on-site assembly support, the project images show how the 38-booth office pod project was prepared and coordinated across multiple floors.

Project FAQ and Request Options

Why did this project use 1P, 4P, and 6P booths together?

The project needed different booth capacities for different office tasks. 1P office pods were planned for individual communication points, while 4P meeting pods and 6P meeting booths supported small meetings, group discussions, and visitor reception across the four-floor office layout.

How were the booths planned across four floors?

The 38 booths were planned across multiple office floors instead of being grouped into one single booth area. When planning booth placement, the designer considered workstation distribution and corridor locations, placing the booths along suitable wall-side areas where possible to save space.

Why was the packing method adjusted for this project?

The project site had specific moving conditions, including a long moving distance from the unloading point to the elevator, uneven ground, and limited forklift access along the moving path. The packing method was adjusted to a loose packing arrangement to support on-site sorting, handling, and movement after arrival.

What preparation was done before packing?

Before final packing, different booth sizes and model types were trial assembled as pre-shipment project references. Photos and video references were prepared so the project team could refer to booth structure, model types, and assembly sequence before the components were organized for delivery.

Was installation support provided for this project?

Yes. Factory-arranged site-side assembly support was provided for this project. For this project, four installers completed the on-site assembly work for 38 booths over three days. For similar projects, installation support should be reviewed based on project location, site readiness, order scope, and local assembly conditions.

What does “completed handover” mean in this case?

Completed handover means the site assembly stage was completed and the project handover was confirmed after assembly. In this case page, it is used as a project status description, not as a customer usage result, employee feedback, or post-installation performance claim.

Were spare parts prepared for the project?

Yes. Spare parts were prepared as part of the project handover support. The prepared items included door handles, locks, LED lights, fans, and socket ports. Spare parts for similar projects can be reviewed based on booth quantity, model mix, packing method, and project requirements.

What should buyers provide for a similar multi-floor office pod project?

For a similar project review, buyers can share the floor plan, planned booth quantity, preferred booth capacities, destination country, site access conditions, packing needs, and any acoustic, VOC, installation, or documentation requirements. This helps the project team review the suitable 1P / 4P / 6P pod mix, layout direction, packing preparation, and project support path.